Operations Update

9 May 2018 07:00

RNS Number : 4293N
Amerisur Resources PLC
09 May 2018
 

9 May 2018

 

Amerisur Resources Plc ("Amerisur" or the "Company")

 

 Operations Update

 

Amerisur Resources Plc, the oil and gas producer and explorer focused on South America, is pleased to provide an update on operations in Colombia.

 

Platanillo N Sand Drilling

 

The Company is pleased to report good progress on the civil works, a 3.8km new road and a location with three drilling cellars. This progress has been made in spite of adverse weather conditions and the discovery of unconsolidated zones on the route which required additional works to stabilise. The construction is expected to be completed in June, after which Rig D10 will be mobilised to drill Pintadillo-1, the first of up to three wells targeting the N Sand anomaly, which has been identified on 3D seismic. Pintadillo-1 will be a slightly deviated well, with a planned total measured depth of 8,448ft, and is expected to take less than a month to drill and log.

 

The N Sand anomaly at Pintadillo is one of four such anomalies identified by the Company in the central part of the Platanillo block. It is estimated to hold P50 resources of 11.44 mmbo.

 

Put-8 Drilling

 

Amerisur has been informed by the Operator of block Put-8, Vetra Exploration and Production (50%), that the drilling contractor has been slightly delayed in the completion of their previous contract and the spudding of Miraparriba-1 is now planned to begin in June 2018. Miraparriba-1 will be drilled as a directional well to the Miraparriba structure within the Put-8 block.

 

The Miraparriba structure is a low risk U and T sand light oil structural target covered by 3D seismic with gross P50 recoverable resources estimated at 4.4 mmbo by the Operator.

 

Put-8 is a 102,799 acre block which lies adjacent to the west of the Platanillo field.

 

CPO-5

 

The Operator (ONGC Videsh Ltd, 70%) has informed the Company that the preparations for the spudding of the well Indico-1 continue to advance despite adverse weather conditions in the area. The rig is now expected to mobilise in the latter part of June 2018. Mariposa-1 continues to produce in a stable manner and the operation to perforate additional zones in the well is expected to be performed within the next month.

 

Indico-1 is targeting the same play as the successful Mariposa-1 well, but is further up dip in a larger structure. The Operator estimates a gross P50 recoverable resource at Indico-1 of 10.3 mmbo.

 

CPO-5 is located to the south of the prolific Llanos 34 block and to the east of the Corcel fields. The block includes the producing Mariposa-1 well and the evaluation area related to the Loto-1 oil discovery.

 

John Wardle, CEO of Amerisur said:

 

"We are gearing up for a busy period of exploration drilling, targeting 26 mmbo of gross resource over the first three wells."

 

ENDS

Enquiries:

 

Nick Harrison, CFO

Amerisur Resources

 

Tel: +44 (0)330 333 8246

Billy Clegg/Georgia Edmonds

Tel: +44 (0)203 757 4980

Camarco

 

Callum Stewart/Nicholas Rhodes/Ashton Clanfield

Stifel Nicolaus Europe Limited

Tel: +44 (0)20 7710 7600

Chris Sim/George Price

Tel: +44 (0)207 597 4000

Investec

Darrell Uden/Marcus Jackson

RBC Capital Markets

 

Tel: +44 (0)207 653 4000

 

 

Notes to editors

Amerisur Resources is an independent full-cycle oil and gas company focused on South America, with assets in Colombia and Paraguay and production from two fields in Colombia. In 2016 Amerisur successfully built and is 100% owner of the strategic OBA oil transfer line into Ecuador.

 

In Colombia, the Company is operator and has a 100% working interest in the Platanillo block which includes the Platanillo producing field in the Putumayo basin, and holds a 30% non-operated working interest in the CPO-5 block containing the Mariposa-1 producing field in the Llanos basin. Amerisur is currently producing approximately 5,000 bopd while Platanillo production wells are undergoing maintenance.

 

Amerisur has a strong position in the Putumayo basin and has a cluster of near term activity assets around the OBA export line.

 

Standard: These assessments are made in accordance with the standard defined in the SPE/WPC Petroleum Resources Management System (2007).

 

Competent person: Technical information in this announcement has been reviewed by John Wardle Ph.D., the Company's Chief Executive. John Wardle has 32 years' experience in the industry, having worked for BP, Britoil, Emerald Energy and Pebercan, and is a trained drilling engineer.

 

This announcement contains inside information as defined in EU Regulation No. 596/2014 and is in accordance with the Company's obligations under Article 17 of that Regulation.

 

www.amerisurresources.com 

 

Glossary

 

"mmbo"

million barrels of oil

"bo"

barrels of oil

"P50 resources"

the best estimate of the quantity of resources that will actually be recovered. It is equally likely that the actual remaining quantities recovered will be greater or less than the best estimate

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLGMGGKGRVGRZZ
Date   Source Headline
27th Jan 20167:00 amRNSIssue of Equity
26th Jan 20167:00 amRNSAcquisition of Platino Energy Ltd
19th Jan 20164:35 pmRNSPrice Monitoring Extension
23rd Dec 20153:24 pmRNSReplacement - Adoption of Financial Reporting Std
23rd Dec 20157:00 amRNSAdoption of Financial Reporting Standard
16th Dec 20157:00 amRNSDirector's Interests
1st Dec 20152:10 pmRNSBLOCK LISTING SIX MONTHLY RETURN
1st Dec 20157:00 amRNSEcuador-Colombia Interconnector Update
6th Nov 20157:01 amRNSLoto-2 Update
13th Oct 20157:00 amRNSLoto-2 Update
6th Oct 201512:09 pmRNSIssue of Equity
28th Sep 20157:00 amRNSInterim Results
22nd Sep 20157:00 amRNSLoto-2 Update
15th Sep 20153:25 pmRNSHolding(s) in Company
7th Sep 20157:00 amRNSOperations Update
1st Jul 20153:05 pmRNSIssue of Equity
29th Jun 201511:30 amRNSAcquisition of Petrodorado South America SA
12th Jun 20157:00 amRNSEcuador-Colombia Interconnector Update
1st Jun 20151:50 pmRNSBLOCK LISTING SIX MONTHLY RETURN
22nd May 20152:44 pmRNSHolding(s) in Company
8th May 20157:00 amRNSPipeline Update
6th May 20151:12 pmRNSResult of AGM
29th Apr 20157:00 amRNSOperations Update
22nd Apr 20154:15 pmRNSDirector Dealings
22nd Apr 20157:00 amRNSDirector Dealings
21st Apr 20155:24 pmRNSBoard Change
21st Apr 20157:00 amRNSDirector Dealings
13th Apr 201510:29 amRNSNotice of AGM
13th Apr 20157:00 amRNSDirector Dealings
13th Apr 20157:00 amRNSDirector Dealings
9th Apr 20157:00 amRNSDirector Dealings
8th Apr 20157:05 amRNSLTIP Awards Update
8th Apr 20157:00 amRNSFinal Results
2nd Apr 20155:12 pmRNSLTIP Awards Update
1st Apr 20157:00 amRNSReserves and Resources Update
11th Mar 20157:00 amRNSNotice of Results
13th Feb 20151:30 pmRNSDirector purchase of shares
9th Feb 20157:01 amRNSGrant of Share Options
9th Feb 20157:00 amRNSPipeline Update
2nd Feb 20157:00 amRNSRevised 2015 Plan, Outlook and Guidance Statement
19th Jan 20156:20 pmRNSHolding(s) in Company
5th Jan 20157:00 amRNSDirector Appointment
3rd Dec 201411:13 amRNSNotification of Major Interest in Shares
1st Dec 201410:32 amRNSBlock Listing Six Monthly Return
27th Nov 20149:11 amRNSNotification of Major Interest in Shares
22nd Oct 20147:00 amRNSNew Exploration License in Colombia
7th Oct 20147:00 amRNSPlatanillo-20 Update
30th Sep 20147:00 amRNSHalf Yearly Report
26th Aug 20147:00 amRNSPlatanillo-18 Update
19th Jun 20147:00 amRNSOperations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.