Operations Update

9 May 2018 07:00

RNS Number : 4293N
Amerisur Resources PLC
09 May 2018
 

9 May 2018

 

Amerisur Resources Plc ("Amerisur" or the "Company")

 

 Operations Update

 

Amerisur Resources Plc, the oil and gas producer and explorer focused on South America, is pleased to provide an update on operations in Colombia.

 

Platanillo N Sand Drilling

 

The Company is pleased to report good progress on the civil works, a 3.8km new road and a location with three drilling cellars. This progress has been made in spite of adverse weather conditions and the discovery of unconsolidated zones on the route which required additional works to stabilise. The construction is expected to be completed in June, after which Rig D10 will be mobilised to drill Pintadillo-1, the first of up to three wells targeting the N Sand anomaly, which has been identified on 3D seismic. Pintadillo-1 will be a slightly deviated well, with a planned total measured depth of 8,448ft, and is expected to take less than a month to drill and log.

 

The N Sand anomaly at Pintadillo is one of four such anomalies identified by the Company in the central part of the Platanillo block. It is estimated to hold P50 resources of 11.44 mmbo.

 

Put-8 Drilling

 

Amerisur has been informed by the Operator of block Put-8, Vetra Exploration and Production (50%), that the drilling contractor has been slightly delayed in the completion of their previous contract and the spudding of Miraparriba-1 is now planned to begin in June 2018. Miraparriba-1 will be drilled as a directional well to the Miraparriba structure within the Put-8 block.

 

The Miraparriba structure is a low risk U and T sand light oil structural target covered by 3D seismic with gross P50 recoverable resources estimated at 4.4 mmbo by the Operator.

 

Put-8 is a 102,799 acre block which lies adjacent to the west of the Platanillo field.

 

CPO-5

 

The Operator (ONGC Videsh Ltd, 70%) has informed the Company that the preparations for the spudding of the well Indico-1 continue to advance despite adverse weather conditions in the area. The rig is now expected to mobilise in the latter part of June 2018. Mariposa-1 continues to produce in a stable manner and the operation to perforate additional zones in the well is expected to be performed within the next month.

 

Indico-1 is targeting the same play as the successful Mariposa-1 well, but is further up dip in a larger structure. The Operator estimates a gross P50 recoverable resource at Indico-1 of 10.3 mmbo.

 

CPO-5 is located to the south of the prolific Llanos 34 block and to the east of the Corcel fields. The block includes the producing Mariposa-1 well and the evaluation area related to the Loto-1 oil discovery.

 

John Wardle, CEO of Amerisur said:

 

"We are gearing up for a busy period of exploration drilling, targeting 26 mmbo of gross resource over the first three wells."

 

ENDS

Enquiries:

 

Nick Harrison, CFO

Amerisur Resources

 

Tel: +44 (0)330 333 8246

Billy Clegg/Georgia Edmonds

Tel: +44 (0)203 757 4980

Camarco

 

Callum Stewart/Nicholas Rhodes/Ashton Clanfield

Stifel Nicolaus Europe Limited

Tel: +44 (0)20 7710 7600

Chris Sim/George Price

Tel: +44 (0)207 597 4000

Investec

Darrell Uden/Marcus Jackson

RBC Capital Markets

 

Tel: +44 (0)207 653 4000

 

 

Notes to editors

Amerisur Resources is an independent full-cycle oil and gas company focused on South America, with assets in Colombia and Paraguay and production from two fields in Colombia. In 2016 Amerisur successfully built and is 100% owner of the strategic OBA oil transfer line into Ecuador.

 

In Colombia, the Company is operator and has a 100% working interest in the Platanillo block which includes the Platanillo producing field in the Putumayo basin, and holds a 30% non-operated working interest in the CPO-5 block containing the Mariposa-1 producing field in the Llanos basin. Amerisur is currently producing approximately 5,000 bopd while Platanillo production wells are undergoing maintenance.

 

Amerisur has a strong position in the Putumayo basin and has a cluster of near term activity assets around the OBA export line.

 

Standard: These assessments are made in accordance with the standard defined in the SPE/WPC Petroleum Resources Management System (2007).

 

Competent person: Technical information in this announcement has been reviewed by John Wardle Ph.D., the Company's Chief Executive. John Wardle has 32 years' experience in the industry, having worked for BP, Britoil, Emerald Energy and Pebercan, and is a trained drilling engineer.

 

This announcement contains inside information as defined in EU Regulation No. 596/2014 and is in accordance with the Company's obligations under Article 17 of that Regulation.

 

www.amerisurresources.com 

 

Glossary

 

"mmbo"

million barrels of oil

"bo"

barrels of oil

"P50 resources"

the best estimate of the quantity of resources that will actually be recovered. It is equally likely that the actual remaining quantities recovered will be greater or less than the best estimate

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLGMGGKGRVGRZZ
Date   Source Headline
22nd Mar 201711:03 amRNSHolding(s) in Company
20th Mar 20172:28 pmRNSNotification of Major Interest in Shares
16th Mar 20177:44 amRNSCaguan-Putumayo Basin Acquisitions
10th Mar 20174:35 pmRNSPrice Monitoring Extension
9th Mar 201712:47 pmRNSPlatanillo Operations Update
9th Mar 20177:00 amRNSMonthly Production and OBA Throughput Update
31st Jan 201711:34 amRNSTotal Voting Rights
27th Jan 20177:00 amRNSHolding(s) in Company
24th Jan 20177:00 amRNSPlatanillo 24 Update
19th Jan 20175:05 pmRNSHolding(s) in Company
9th Jan 20177:24 amRNSPlatanillo-24 Update
3rd Jan 20177:00 amRNSBoard Changes and Remuneration Update
23rd Dec 20167:00 amRNSSpudding of Platanillo 24
22nd Dec 201610:51 amRNSDirector/PDMR Shareholding
20th Dec 20167:00 amRNSColombia Asset Acquisition
16th Dec 20167:00 amRNSColombia Business Update
2nd Dec 20169:51 amRNSBlock listing six monthly return
1st Nov 20167:00 amRNSHolding(s) in Company
27th Oct 20161:12 pmRNSOBA Pipeline Operational
27th Oct 201612:45 pmRNSOBA Pipeline Operational
3rd Oct 20162:55 pmRNSHolding(s) in Company
3rd Oct 20167:00 amRNSOBA Pipeline Update
21st Sep 20167:00 amRNSAnalyst site visit and 2017 guidance
15th Sep 20167:00 amRNSInterim Results
12th Jul 20167:00 amRNSOperations Update
4th Jul 201612:21 pmRNSHolding(s) in Company
27th Jun 20163:59 pmRNSHolding(s) in Company
23rd Jun 20162:35 pmRNSCommencement of Drilling on Platanillo Field
17th Jun 20167:05 amRNSCoati Update
17th Jun 20167:05 amRNSOperations Update
3rd Jun 20167:00 amRNSOperations Update
1st Jun 20169:02 amRNSBLOCK LISTING SIX MONTHLY RETURN
31st May 20167:00 amRNSIndependent Non-executive Director Appointment
23rd May 20163:31 pmRNSLong Term Incentive Plan ("LTIP") Awards
4th May 20163:20 pmRNSResult of AGM
4th May 20169:30 amRNSAGM Statement
22nd Apr 20167:00 amRNSSpudding of Jaguareté-1, Paraguay
8th Apr 20167:00 amRNSNotice of AGM
7th Apr 20167:00 amRNSFinal Results for the year ended 31 December 2015
5th Apr 20169:17 amRNSHolding(s) in Company
29th Mar 20167:00 amRNSReserves Update
16th Mar 20167:00 amRNSIssue of Equity
14th Mar 20164:47 pmRNSHolding(s) in Company
14th Mar 20164:46 pmRNSHolding(s) in Company
14th Mar 20167:00 amRNSHolding(s) in Company
9th Mar 201610:24 amRNSResults of placing
9th Mar 20167:00 amRNSProposed Placing
4th Mar 20161:40 pmRNSHolding(s) in Company
29th Feb 20167:00 amRNSChange of Adviser
18th Feb 20167:00 amRNSEcuador-Colombia Interconnector Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.