Operations Update

13 Jul 2011 07:00

RNS Number : 2769K
Amerisur Resources PLC
13 July 2011
 



13th July 2011

 

Amerisur Resources Plc ("Amerisur" or the "Company")

 

Operations Update

Amerisur Resources Plc, the oil and gas producer and explorer focused on South America, announces today an update on operations in Colombia and Paraguay.

 

Platanillo

 

The Company applied for a modification of the Platanillo Global Environmental License to the Ministry of Environment, Housing and Territorial Development (MAVDT) on 21st January 2011. That modification contemplated the construction of an access road to the southern part of the field and 8 new drilling locations within that section. The Company has maintained a close contact with MAVDT and has promptly provided all the information and assistance required by the environmental authorities. The proposal is under review by MAVDT.

 

It is expected that the drilling programme will be underway during Q4 2011. Given the delays occasioned by the permitting process the Company expects to complete 3 new wells during 2011, however the drilling programme would continue consecutively should results merit, thus completing the total of 6 new wells during H1 2012.

 

 

San Pedro Block Paraguay

 

The 13,000 km Aeromagnetometry programme was completed on time and on budget and Fugro is well advanced with the data processing. The Company expects to begin interpretation during July 2011.

 

 

John Wardle, CEO, said:

 

"The tremendous growth of activity in the Petroleum and Mining sectors in Colombia has placed an unprecedented load upon regulatory resources. This is an extraordinary situation, never seen before in the Colombian industry and has had an extraordinary effect upon the operations of all Operators in the country. Our respect for the environment where we work is paramount and is an integral part of our business. I believe we have maintained these high standards in our work and proposals to date. All preparations for the drilling programme are complete, and have been so for some time, hence once we receive the approval of the environmental modification I expect to achieve rapid progress."

 

Competent person: Technical information in this announcement has been reviewed by John Wardle Ph.D., the Company's Chief Executive. John Wardle has 25 years' experience in the industry, having worked for BP, Britoil, Emerald Energy and Pebercan, and is a trained drilling engineer.

 

ENQUIRIES:

 

 

Billy Clegg/Caroline Stewart,

Financial Dynamics

 

 

 

Tel: +44 (0)207 831 3113

 

Martin Eales

RBC Capital Markets

 

Tel: +44 (0)207 653 4000

 

Notes to editors

 

 

 

The Platanillo contract is a commercial area held with the Agencia Nacional de Hidrocarburos located in the Putumayo basin of southern Colombia, near the border with Ecuador. The Company has a 100% interest in this area. As a commercial area, the Platanillo block has no exploration commitments. The exploitation period is 24 years, with the facility to extend to the end of field economic life should the Company wish to do so. The Exploitation Area was extended during 2010 up to the national boundary to the south of the previous block limit.

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCQLLFFFDFEBBZ
Date   Source Headline
20th Jun 20114:35 pmRNSPrice Monitoring Extension
24th May 20114:41 pmRNSBlock Listing Application
10th May 20112:20 pmRNSResult of AGM
10th May 20117:00 amRNSAGM Statement
12th Apr 20117:00 amRNSFarm Out Agreement Fenix Contract
6th Apr 20117:00 amRNSResults for the nine months ended 31 December 2010
3rd Mar 20118:45 amRNSIssue of shares
16th Dec 20107:00 amRNSInterim Results
24th Nov 20107:00 amRNSOperations Update
14th Oct 20107:00 amRNSOperations Update
4th Aug 20104:17 pmRNSResult of AGM
4th Aug 20108:00 amRNSAGM Statement
1st Jul 20107:00 amRNSPreliminary Results
3rd Jun 201011:00 amRNSHolding(s) in Company
5th May 20107:00 amRNSAppointment of Nominated Adviser and Broker
30th Apr 20107:00 amRNSPlacing
12th Apr 20107:00 amRNSOperations Update Isabel-1
22nd Mar 20107:00 amRNSOperations Update
17th Mar 20102:45 pmRNSAmendment to Share Options
17th Mar 20107:00 amRNSOperations Update
8th Feb 20107:00 amRNSContractual Update Colombia
5th Feb 20107:00 amRNSExercise of Options
4th Feb 20107:00 amRNSColombia Operations Update
2nd Feb 201012:04 pmRNSHolding(s) in Company
23rd Dec 200911:11 amRNSOperations Update Colombia and Grant of Options
16th Dec 20097:00 amRNSInterim Results
10th Dec 200910:26 amRNSHolding(s) in Company
9th Dec 200910:32 amRNSHolding(s) in Company (Replacement)
9th Dec 200910:17 amRNSHolding(s) in Company
3rd Dec 20097:00 amRNSOperations Update Colombia
16th Nov 20093:49 pmRNSExercise of Options
16th Nov 20097:00 amRNSDrilling Update Colombia
5th Nov 20097:00 amRNSColombia Drilling Update
26th Oct 20097:00 amRNSColombia Update
19th Oct 20097:00 amRNSDrilling of Iguasa-1 commences
5th Oct 20097:00 amRNSGrant of Share Options
17th Sep 20097:00 amRNSPlatanillo - Assignment of Interest
10th Sep 20098:30 amRNSUpdate re Iguasa-1
2nd Sep 20097:00 amRNSUpdate re Paraguay
5th Aug 200911:25 amRNSResult of AGM
5th Aug 20097:00 amRNSAGM Statement
6th Jul 20097:00 amRNSPreliminary Results
15th Jun 20097:00 amRNSChange of Name of Nominated Adviser and Broker
29th May 20097:00 amRNSParaguay - Operational Update
10th Mar 20097:00 amRNSParaguay - Operational Update
2nd Mar 20097:00 amRNSUpdate re Platanillo
30th Dec 20087:00 amRNSInterim Results
13th Nov 20087:00 amRNSANH Mini Ronda - Amerisur Qualification
24th Oct 20087:00 amRNSDirector/PDMR Shareholding
22nd Oct 20087:00 amRNSPlatanillo - Operations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.