RE: Roald Goethe director buying28 Jun 2025 12:37
It's worth skimming through Petrocom 2025 Outlook Report available here
https://petrocom.gov.gh/reports/
p.17 shows there is zero production from 8 of 26 oil Jubilee producers. Elsewhere amongst other things the report mentions
"TGL continued activities on the upgrade for the gas handling capacities of the equipment for gas compression in 2024. These activities include low pressure gas compressor coolers change-out and installation of lift frame for IGC cooler change-out. In addition, TGL conducted an activity to improve the performance of the water injection into the field which was targeted to increase the water injection volumes thereby reducing high gas injection needed to mitigate increasing Gas Oil Ratio (GOR)."
"There was reduction in production volumes in the month of November 2024 and was attributed to the dual riser flow trial between riser 10 and riser 11 on the Jubi lee field to mitigate slugging during oil production and the subsequent process shutdown of the oil train due to an upset caused by slugging in the HP separator. The dual flow trail was aborted and resumption of production with a single riser production."
"In 2025, the major activity expected on the Jubilee field is the planned maintenance shutdown of the field. The major driver of the shutdown aims to address the safety and integrity of the FPSO KNK (safety, ABS Class SS7, M&I and plant improvement). Due to the activities that needed to be undertaken pre- and during the shutdown, an accommodation vessel was contracted to support the activities for four (4) months. The following activities are part of the major drivers for the shutdown.
COT hatch weld repair
Maintenance and integrity activities on the LP flare KOD, TEG reboiler, TEG surge drum
Replacement of inlet gas cooler (IGC)
Seawater/Cooling medium exchangers plate replacement
PLET tieback replacement.
Other activities including the subsea inspection and repairs, UWILD, GTG engine change-out and equipment maintenance as well as corrosion management will be undertaken in 2025. The riser Tracon clamps activities are also expected to continue with the acceptance tests and installation in 2025."