RE: Re: PEPR25 Nov 2019 14:58
Fira,
The relevance of my post is simple, certain posters on here just seem to want to moan and yet have not done any research apart from reading this board.
Gorsuch says they should have been doing a PEPR 6 or 9 months ago, they did!
Sammybow states that they said they would be producing by Q3 2019, they did!
Dotcom worries about a vast bond, they paid $50kAUS bond for phase 1 - the restart of the heaps.
They submitted a PEPR in February 2019 and that was approved on 3rd April 2019, that PEPR was for the restart and processing of the heaps at MoL (within 2 years), moving the processing plant then to start mining and production at Lorna Doone and Lynda (within 3 years), finally to move the processing plant back to MoL to trial mine Paltridge North ( within 4 years).
This changed and they are submitting another PEPR to start mining at Paltridge North and Rosmann East first, the current PEPR does not cover this, but a lot of the data is the same and relevant as the start up of the MoL plant uses it.