CO2 EOR Project Schedule16 Jun 2019 17:06
Just looking at the CO2 EOR Project Schedule , It would be great if Paul updated us on this since i believe we are not on schedule.
Phase 1. Up to 30 days scheduled Feb 2019 , Repressurise reservoir - inject CO2 up to 2,000psi into downdip wells At - 5 X and AT-12
Phase 2 90 Days , March, April May.
CO2 Injection updip in At - 4 & At - 13 for pressure maintenance and production at 5X/At-13,
Monitor and very if necessary CO" injection rates and volume
Phase 3 240 - 250 days June to Feb 2020
CO2 Injection updip in At - 4 & At - 13 for pressure maintenance and production at 5X/At-13 & potentially from up to 6 existing wells in the At 4 Block - monitor for CO2 breakthrough
To me , looking at phase 2 , We should have been in production by the end of May.
Paul needs to update on what is happening
This information can be on the PRD Website