RE: Broker research5 Mar 2022 16:23
Dear All - please find below Canaccord's reaction to yesterday's news from Talitha and Theta West. Note is dated 4/3/22.
Pantheon Resources
Oil and Gas, Exploration and Production | Flash Update
Talitha testing ending, equipment to mobilise to Theta West
PANR-AIM | Price 135p | Market Cap £1,008.1M
SPECULATIVE BUY Unchanged
PRICE TARGET 220p Unchanged
Full focus turns to Theta West well testing
Talitha SMD reservoir test - disappointment as downhole blockage impacts result
After perforating and stimulating a 10ft interval of the SMD reservoir, and after a three day blizzard-related interruption, the SMD test produced only 45% of the fracture fluid, no formation water, and only small amounts of light oil (34 API) over a very short period. The well then stopped flowing entirely.
As no reservoir fluids were produced — apart from these very small amounts of oil — the company and external consultants consider this is due to a blockage in or around the well-bore. Pantheon believes that the SMD reservoir should have flowed at better rates than the two previous tests (Basin Floor Fan, BFF, 73 bopd; Slope Fan 45 bopd) and certainly in line with or better than the pre-drill anticipated 50-80 bopd.
Theta West - successful remedial work, now ready to test
Pantheon has successfully drilled out the cement plug in the well-bore and set a new liner. The well is now ready for perforation, stimulation, and flow-testing.
The coil tubing unit and ancillary equipment will mobilise imminently from Talitha to Theta West, as soon as the large drilling rig at Theta West demobilises.
We understand that the timetable should allow the testing phase of the BFF at Theta West to commence around mid March providing two, or perhaps three weeks to complete the testing programme before all equipment has to leave the site as temperatures warm.
Canaccord Genuity view:
Clearly, there is some disappointment that the final, and perhaps the best, test in Talitha on the original primary target reservoir has not been possible. A good result could have provided definitive support for potential commerciality of the SMD reservoir at the site.
However, we think the positive news regarding successful remedial work at Theta West and the decision to move testing equipment early to carry out the test is very sensible. The testing of the Theta West BFF reservoir was always a key part of this phase of Pantheon's 2022 operational programme and those results should be in by end of March.
Valuation and rating: We maintain our 220p target price and SPECULATIVE BUY rating.