Permitting Consultations16 Sep 2020 09:48
Following a recent request for any information to the Permitting Consultations team at Newport, they have very kindly sent a response this morning:
Dear
Thanks for your enquiry regarding the Uskmouth Power Station permit substantial variation application for proposed plant conversion. Following the initial public consultation on the Duly Made application, we are still determining the application in detail. This requires extensive consideration of the technical detail of the proposals and often takes some time. We have twice formally asked the applicant for further information on specific aspects of the proposal, via Schedule 5 notices, and have asked for other clarifications via email. This is normal in a complex determination, and we are not yet in receipt of all of the information we need to make our decision.
There is a dedicated Natural Resources Wales web page giving detail of the Uskmouth Power Station application, linked below:
https://naturalresources.wales/about-us/news-and-events/statements/uskmouth-power-station-application-to-change-environmental-permit/?lang=en .
I have arranged for minor updates to it this week, to reflect progress to date. On this page, there is a link to our public register, where you can track in detail the ongoing correspondence regarding the determination.
In due course when we have made our determination, the outcome or draft decision will be advertised on our website. If we are minded to grant the variation, there will be a period of public consultation on the decision. The website explains this more.
Kind regards
Permitting Consultations