RE: DFS?24 Jul 2025 18:45
Hi Damers
A DFS requires a class 3 estimate (AACE). That requires a certain level of design say 30 to 40% level. So whilst they could have completed everything else in the estimate the critical path of the estimate will be dependent on the design being completed for the last part(s) which in this case will be the TSF and the TAM part. They could I suppose over engineer by making assumptions to do it quickly (though that will mean additional cost is included in the estimate). Maybe they will do that and it will be this year. Ultimately though I dont really see the point. They need the full design of the TSF for the license. If you give me the level of design I need ill do the estimate in less than a month (not for a mine but in the fields I work - so basically infrastructure). They work to a different plus or minus than I do in my field based on the PFS (class 4 estimate) which was 25% up or down. But a DFS is supposed to be more accurate. I doubt G-mining will want to rush it. But they will have their own processes and systems.