RE: Loxley9 Apr 2022 09:12
"So assuming it goes in UKOG's favour then how long will it be before oil is coming out of the ground "
Never - because it's gas......................
If it passes then they will need to raise cash to do it . Site prep will be 3 months and assuming they can get a decent rig they could be on site 5 months after PP is granted then 2 months to drill the well, 1 month to do a basic test so end Q1 2023. Then they have o decide if they need a long term test - (=waste another year) or drill an appraisal (almost certainly necessary after what happened at Godley Bridge) say drill by end 2023 . Possibly on production mid/late 2024 at the earliest.