RE: Mercuria and the hedge10 Apr 2022 19:55
The critical phrase is:-
"the deliverability of the existing two wells as being likely to be greater than 5 mmscfd."
That is NOT a certainty, it's an opinion
For the avoidance of doubt they said:-
A.The lenders technical advisers and Angus evaluated the deliverability of the existing two wells as being likely to be greater than 5 mmscfd. The reasoning was twofold. In the last years of delivery to the old Conoco refinery, average production was constrained by persistent issues with the main compressor at Theddlethorpe. Secondly it was the view of technical experts that, following a prolonged shut-in, the two wells should have improved deliverability in the first 18 months or so of operations. This is because prior to shut in there was an area of reduced pressure around the producing wells. Since then the pressure has equilibrated across the field resulting in significantly higher pressure around the producers. So it is our view that the hedged production should be able to be covered by these two wells in the event of failure of the sidetrack
B. Finger in the air: Worst 7mmscfd, Probable 10mmscfd, Best 10mmscfd (but extended for a longer period of time) Note, the combined deliverability of the three wells will exceed the production rate during the plateau period which is limited to 10mmscfd by virtue of the process equipment.
C. We believe that simultaneous operations are feasible on this site but we do need to do much more work on how such operations would be conducted.