RE: Re Velociraptor18 May 2023 13:53
Following discussions with selected drilling contractor, Major Drilling ("Major"), a spud date for the Velociraptor 1 well has been confirmed for June 2023 following completion of Major's current programme for another operator. All required equipment for the well is in country. Field work has commenced to make ready the water supply well that will be used to supply the operation. Site construction will commence during May in good time for the scheduled June spud. The well is expected to take around 30 days to drill to a prognosed total depth of c.1500m.