ShinyBits Telfer update25 Sep 2024 05:41
My understanding is that the tailings dam is good to go, and the capacity increase for TSF8 will be ongoing and should be enough for at least 10 to 15 years.
Train 1 has been started up, at a reduced capacity and gradually ramping up while any restart issues are ironed out.
I’ll know a bit more in a couple of days after a chat but I believe train 2 was ready to start but a mechanical issue came up that will take 3 or 4 days to repair, then T2 will be started as well.
I’ve seen a picture of the stockpile (already crushed) ready for the mills, and it’s enormous!
I get the impression that lots of folks there are cautiously optimistic at worst, excited at best to be extracted from under the feet of a huge multinational, and in to the clutches of a smaller company that actually cares about Telfer and its future.