Predicting a time line20 Jan 2026 12:18
NOW — Jan 2026
DFS for the Cínovec published on 23 December 2025, confirming a 26+ year mine life and steady‑state production of 37,500 tonnes per year of battery‑grade lithium carbonate with strong project economics.
The full EIA was formally submitted on 31 December 2025, completing the required two‑stage process and meeting EU Just Transition Fund compliance. Cínovec has been designated a Strategic Project under the EU CRMA and classified by the Czech government as a Strategic Deposit, both of which accelerate and streamline the permitting process
→ Project now entering the final permitting phase.
Q1 2026 (Feb–Mar 2026)
EIA Review & Public Consultation, ministry begins formal review of the full EIA; public consultation expected “early 2026.”
Outcome: EIA progresses through technical reviews and consultation.
Q2 2026 (Apr–Jun 2026)
EIA Approved & JTF requirements met, given CRMA fast‑tracking + Czech strategic designation, approval is likely before June (possibly earlier).
Outcome: EIA approved, unlocks full funding access, clears path to final permitting (mining area consolidation)
Q3 2026 (Jul–Sep 2026)
Final Investment Decision (FID)
With DFS done, EIA approved, and grants secured (up to €360M Czech + €36M EU JTF), the project is fully prepared for FID.
Outcome: FID achieved (likely Q3 2026), begin Early Works, site prep at the Prunerov EPR1 processing plant site begins, access preparation, utilities, geotechnical prep start.
Q3 2026 – Q4 2027
Construction Phase (Mine + Processing Plant)
What happens : underground twin declines developed, ventilation, support, underground services, processing plant construction at EPR1, flotation circuit + hydromet line installation, tailings + backfill systems installed, workforce surge.
Offtake agreements executed to support financing (likely in parallel)
Basis for duration: DFS defines extensive mine/plant development with ~2‑year build time.
Outcome: major build-out spanning ~24 months, mechanical completion achieved and Pre-Commissioning of systems ongoing Q4 2027
Q1–Q3 2028 - Dynamic Commissioning Phase
Activities: commissioning of underground mine systems, concentrator, hydrometallurgical plant producing Li₂CO₃.
First low-volume trial batches and process optimisation
Outcome: Operational readiness achieved and Ramp-up to commercial production begins
Q4 2028 – Q1 2029 - FIRST LITHIUM SHIPMENT of battery-grade lithium carbonate (Li₂CO₃) leaves the Cínovec processing plant.