RE: RNS16 May 2023 08:48
With the SNAM connection and transmission arrangements finalised, Po Valley Operations has initiated the process of recovering €757,000 performance bond funds (100% basis - €280,090 net to Prospex), previously deposited with SNAM
Construction and grid connection has been largely completed on schedule and budget, with only a 3% cost difference to budgeted expenditure. This amounts to ~€132,000 (100% basis), €48,840 net to Prospex. Given the global supply chain concerns the joint venture is delighted with this outcome.
Initial production of PM-1 gas is contingent on the signoff of the final operation and safety inspection. PVO anticipates that this will occur before the end of May 2023.