Zanaga completes re-costing and ore reserve update

Wed, 05th May 2021 10:36

(Sharecast News) - Zanaga Iron Ore Company updated shareholders following completion of the re-costing exercise and ore reserve update on the Zanaga Iron Ore Project on Wednesday.
The AIM-traded firm said the Zanaga project consisted of a 30 million tonnes per annum staged development project, including an 18 million tonnes per annum second stage expansion.

It said an initiative to update the cost estimates associated with the first stage, as outlined in the 2014 feasibility study, had been completed, with external independent technical expert engineering firms engaged by Jumelles - the joint venture company between Zanaga and Glencore - to oversee and provide input into the feasibility study review.

The objective was to ascertain the potential capital and operating costs associated with the construction of the Zanaga project's 12 million tonnes per annum first stage project in the current market environment.

It said the feasibility study review indicated capital and operating cost estimates for the first stage development project remained approximately within the guidance levels outlined in the 2014 study.

Specifically, it said capital expenditure was expected to range between -2.9% and +2.5% of the 2014 feasibility study estimate, or between $2.15bn (£1.54bn) and $2.28bn.

The lower range would depend on the implementation of a number of potential savings opportunities identified by the independent technical experts.

Operating cost estimates were also estimated to be approximately in line with the estimates provided in the 2014 study.

Looking at the ore reserve estimate re-statement, the company said the Zanaga project's 2.1 billion tonne ore reserve estimate had been re-stated by SRK, and updated based on market pricing as at 31 December.

"The Zanaga project team has worked with third party technical experts to re-assess the potential capital and operating costs that could be achieved in the current market for the 12 million tonnes per annum stage one project, as outlined in the 2014 feasibility study," said non-executive chairman Clifford Elphick.

"The review of these figures indicates that the capital and operating costs estimated in 2014 remain valid in today's market environment, encouraging us to continue to pursue pathways available for development of the 30Mtpa staged development project, especially during the current high iron ore price environment."

At 1509 BST, shares in Zanaga Iron Ore Company were down 17.66% at 7.67p.

Related Shares

More News
3 Apr 2024 12:19

EARNINGS AND TRADING: MediaZest optimistic; Volta Finance NAV up

(Alliance News) - The following is a round-up of updates by London-listed companies, issued on Thursday and not separately reported by Alliance News:

2 Jan 2024 14:36

Zanaga extends repayment data on Glencore loan

(Sharecast News) - Zanaga Iron Ore Company announced on Tuesday that it has agreed with Glencore to extend the repayment date of its loan facility.

2 Jan 2024 11:08

Zanaga extends USD1.8 million Glencore loan repayment date to March

(Alliance News) - Zanaga Iron Ore Co Ltd on Tuesday agreed a loan repayment extension with FTSE 1000listed diversified mining firm Glencore PLC.

2 Jan 2024 07:57

LONDON BRIEFING: AstraZeneca, Sanofi's RSV treatment approved in China

(Alliance News) - Stock prices in London are expected to open higher on Tuesday, reacting to a slight expansion in manufacturing activity in China and...

28 Dec 2023 16:46

London close: Stocks slip as US jobless claims top expectations

(Sharecast News) - London's stock markets experienced a modest decline on Thursday, as the day unfolded with a pronounced lack of significant market-m...

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.