(Adds BP no comment)
HOUSTON, March 23 (Reuters) - The 65,000 barrel per day(bpd) gasoline-producing fluidic catalytic cracking unit at BPPlc's 413,500 bpd Whiting, Indiana, refinery remains shutfor repairs on Monday, said sources familiar with plantoperations.
BP's joint-venture 135,000 bpd Toledo, Ohio, refinery wascontinuing the restart of the 55,000 bpd FCCU on Monday, saidsources familiar with that refinery's operations.
A BP spokesman declined to discuss operations at the tworefineries on Monday.
The Whiting refinery FCCU was shut on March 8 and repairshave been underway since that date.
The Toledo refinery FCCU began restarting on March 17 afterbeing shut for about a month of repair work.
BP co-owns the Toledo refinery with Husky Energy (Reporting by Erwin Seba; editing by Andrew Hay)