Kurdistan Operational Update

Mon, 9th Jan 2012 07:00

RNS Number : 1838V
Gulf Keystone Petroleum Ltd.
09 January 2012

?

Not for release, publication or distribution in or into the United States or jurisdictions other than the United Kingdom and Bermuda where to do so would constitute a contravention of the relevant laws of such jurisdiction.

9 January 2012

Gulf Keystone Petroleum Ltd. (AIM: GKP)

("Gulf Keystone" or "the Company")

Kurdistan Operational Update

Gulf Keystone today provides an update on its ongoing exploration and appraisal programme in the Kurdistan Region of Iraq, which includes the Shaikan block, a major discovery with independently audited gross oil-in-place volumes of between 8 billion barrels to 13.4 billion barrels calculated on the P90 to P10 basis with a mean value of 10.5 billion barrels.

Shaikan-4 Appraisal Well

Gulf Keystone continues a well testing programme for the Shaikan-4 appraisal well, drilled 6 km to the west of the Shaikan-1 discovery well, targeting several formations in the Jurassic and Triassic. One well test in the Triassic has been completed and six further tests are planned. Once the testing programme has been completed in all target formations the Company will make the appropriate announcement.

Shaikan-5 Appraisal Well

The Shaikan-5 appraisal well, 6 km to the north-east of the Shaikan-2 appraisal well, is currently drilling at a measured depth of 1,008 metres. After slower than expected drilling progress due to temporary hole stability issues encountered in the shallow formations, the well is now drilling ahead to the estimated total depth ("TD") of 3,500 metres subject to technical conditions.

Shaikan-6 Appraisal Well

The Shaikan-6 appraisal well, 9 km to the east of the Shaikan-2 appraisal well, has drilled to a measured depth of 362 metres and 26" casing has been set. The well will drill to the estimated TD of 3,800 metres subject to technical conditions.

Shaikan Extended Well Test

As part of the ongoing Extended Well Test ("EWT") on the Shaikan block, the output from the Shaikan-1 & 3 EWT facility has been at an average level of 2,520 barrels gross of oil per day from the latter part of November through to the end of 2011, totalling 103,328 barrels gross as of 31 December 2011.

At the end of 2011, Shaikan test production levels were in excess of 4,000 barrels gross of oil per day and are due to increase further after the ongoing upgrade of the Shaikan-1 & 3 EWT facility has been completed and additional test production facilities have been designed and built. The upgraded and additional EWT facilities will allow test production of Shaikan crude to export specification and a subsequent ramp-up of the Company's export operations.

Gulf Keystone is the Operator of the Shaikan block with a working interest of 75 per cent and is partnered with Kalegran Ltd. (a 100 per cent subsidiary of MOL Hungarian Oil and Gas Plc.) and Texas Keystone Inc., which have working interests of 20 per cent and 5 per cent respectively.

Akri-Bijeel Block

According to the Operator's Akri-Bijeel block operational update and 2012 outlook issued on 28 December 2011, the exploration and appraisal programme will continue with two exploration wells (Barkman-1 and Gulak-1) and four appraisal wells (Aqra-1, Bijell-2, Qalati-1 and Qandagul-1) to be drilled in 2012. Following the completion of the Bekhme-1 exploration well testing programme, after the well reached TD at 5,000 metres in the Triassic, the rig is currently moving to the Aqra-1 appraisal well drilling location with the well expected to be tested in H2 2012.

While no commercial inflow of hydrocarbons was encountered in Bekhme-1, new data gained during the well testing programme is a significant contribution to the continuously improving knowledge of this unexplored region, decreasing uncertainty for the remaining Akri-Bijeel prospects.

In addition to the envisaged acquisition of a significant amount of 3D seismic data over the Bijell discovery area, an extended well test is planned for the Bijell-1 discovery well in 2012, similar to the ongoing successful Shaikan-1 & 3 extended well test. The Operator plans to build a surface facility with 10,000 barrels of oil equivalent gross capacity and a 30,000 barrels storage capacity by Q3 2012.

Gulf Keystone has a 20 per cent working interest in the Akri-Bijeel block operated by Kalegran Ltd., a 100 per cent subsidiary of MOL Hungarian Oil and Gas Plc., which holds 80 per cent working interest in the block. Operator's P50 resource estimate for the Akri-Bijeel block is 2.4 billion barrels of oil-in-place.

Ber Bahr-1 Exploration Well

The first exploration well on the Ber Bahr block is drilling at a measured depth of 2,418 metres in the Triassic to the estimated TD of 3,000 metres subject to technical conditions.

Gulf Keystone has a 40 per cent working interest in the Ber Bahr block operated by Genel Energy, which holds a 40 per cent working interest in the block. The Kurdistan Regional Government has a 20 per cent carried interest in the Ber Bahr Production Sharing Contract.The Operator's resource estimate for the Ber Bahr block is 1.5 billion barrels of oil equivalent-initially-in-place.

John Gerstenlauer, Gulf Keystone's Chief Operating Officer commented:

"As an important addition to Gulf Keystone's aggressive exploration and appraisal campaign, the Shaikan Extended Well Test provides us with an opportunity to continue to gain new data and better understanding of this world-class discovery in the Kurdistan Region of Iraq. This early test production is also important to enhance the Company's already extensive commercial and marketing relationships on the ground in anticipation of further optimization of the Shaikan test production facilities and the commencement of the Bijell-1 extended well test on the Akri-Bijeel block in 2012."

Enquiries:

Gulf Keystone Petroleum:

+44 (0) 20 7514 1400

Todd Kozel, Executive Chairman and

Chief Executive Officer


Ewen Ainsworth, Finance Director

Strand Hanson Limited

+44 (0) 20 7409 3494

Simon Raggett / Rory Murphy / James Harris

Mirabaud Securities LLP

+44 (0) 20 7878 3362

Peter Krens

Pelham Bell Pottinger

+44 (0) 20 7861 3232

Mark Antelme

or visit: www.gulfkeystone.com

John Gerstenlauer, the Company's Chief Operating Officer, who has 31 years of relevant experience within the sector and meets the criteria of a qualified person under the AIM note for mining, oil and gas companies, has reviewed and approved the technical information contained in this announcement. Mr. Gerstenlauer is a member of the Society of Petroleum Engineers.

Notes to Editors:

Gulf Keystone Petroleum Ltd. (AIM: GKP) is an independent oil and gas exploration and production company focused on exploration in the Kurdistan Region of Iraq.

Gulf Keystone Petroleum International (GKPI) holds Production Sharing Contracts for fourexploration blocks in Kurdistan.

The Company's shares have traded on the AIM market of the London Stock Exchange since listing on 8th September 2004.

Gulf Keystone Petroleum Limited is registered in Hamilton, Bermuda with further offices in Erbil, Kurdistan (Iraq), Algiers, Algeria and London, UK.

Gross oil-in-place (or petroleum-initially-in-place) is that quantity of petroleum that is estimated, as of a given date, to be contained in known accumulations prior to production. The range of uncertainty of the oil-in-place (petroleum-initially-in-place) volumes is represented by a probability distribution with a low, mid and high provided: P90 represents at least a 90% probability (high) that the quantities determined to be in place will equal or exceed the low estimate; P50 represents at least a 50% probability (mid) that the quantities determined to be in place will equal or exceed the mid estimate; and P10 represents at least a 10% probability (low) that the quantities determined to be in place will equal or exceed the high estimate.

Not for release, publication or distribution, directly or indirectly, in or into the United States or jurisdictions other than the United Kingdom and Bermuda where to do so would constitute a contravention of the relevant laws of such jurisdiction. This document (and the information contained herein) does not contain or constitute an offer of securities for sale, or solicitation of an offer to purchase securities, in the United States or jurisdictions other than the United Kingdom and Bermuda where to do so would constitute a contravention of the relevant laws of such jurisdiction. The securities referred to herein have not been and will not be registered under the US Securities Act of 1933, as amended (the "Securities Act"), and may not be offered or sold in the United States unless the securities are registered under the Securities Act, or an exemption from the registration requirements of the Securities Act is available. No public offering of the securities will be made in the United States.


This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLUGUUWGUPPPGR






DateSourceHeadlineCategory
01-Oct-14 07:00RNSShaikan Production and Sales UpdateCompany Announcement - General
28-Aug-14 07:00RNSHalf Yearly ReportResults and Trading Reports
12-Aug-14 07:00RNSTR-1 Notification of Major Interest in SharesHolding(s) in Company
07-Aug-14 12:00RNSUpdate on Security SituationCompany Announcement - General
07-Aug-14 10:44RNSAppointment of Non-Executive DirectorsCompany Announcement - General
17-Jul-14 16:33RNS2014 AGM ResultResults and Trading Reports
17-Jul-14 11:00RNSDirectorate ChangesExecutive Changes
25-Jun-14 14:45RNSDirectorate ChangeExecutive Changes
25-Jun-14 07:00RNSDirectorate ChangeExecutive Changes
24-Jun-14 07:00RNSNotice of AGMResults and Trading Reports
16-Jun-14 07:00RNSDirectorate ChangeExecutive Changes
13-Jun-14 07:00RNSShaikan Production UpdateCompany Announcement - General
15-May-14 14:46RNSPost Stabilisation Notice - GKP USDCompany Announcement - General
14-May-14 07:00RNSInterim Management StatementResults and Trading Reports
29-Apr-14 07:00RNS2013 Annual Report and AccountsResults and Trading Reports
17-Apr-14 15:11RNSSettlement of US$250 million debt financingCompany Announcement - General
09-Apr-14 11:33RNSReplacement Stabilisation Notice - GKP USD 3yrCompany Announcement - General
09-Apr-14 07:59RNSUS$250 million debt financingCompany Announcement - General
08-Apr-14 09:16RNSStabilisation Notice - GKP USDCompany Announcement - General
04-Apr-14 16:31RNSFixed Income Investor MeetingsCompany Announcement - General
27-Mar-14 07:00RNS2013 Results AnnouncementResults and Trading Reports
25-Mar-14 07:00RNSFirst Day of Dealings on the Main MarketCompany Announcement - General
20-Mar-14 15:40RNSPublication of ProspectusCompany Announcement - General
19-Mar-14 09:28RNSFixed Income Investor MeetingsCompany Announcement - General
13-Mar-14 07:01RNSPublication of the Competent Person's ReportCompany Announcement - General
13-Mar-14 07:00RNSOperational and Corporate UpdateCompany Announcement - General
24-Feb-14 07:00RNSNotification of proposed AIM cancellationCompany Announcement - General
09-Jan-14 13:43RNS-ROil Export Sales from the Kurdistan Region of IraqCompany Announcement - General
09-Jan-14 07:00RNSOperational and Corporate UpdateCompany Announcement - General
17-Dec-13 07:00RNSExercise of OptionsCompany Announcement - General


Regulatory news is displayed end of day, each day at 19:00.
Sign up for Live Prices
Home  |  Contact Us  |  About Us  |  Careers  |  Advertise with Us  |  Sitemap  |  Terms & Conditions  |  Cookies  |  Privacy


Datafeed and UK data supplied by NBTrader and Digital Look. While London South East do their best to maintain the high quality of the information displayed on this site,
we cannot be held responsible for any loss due to incorrect information found here. All information is provided free of charge, 'as-is', and you use it at your own risk.
The contents of all 'Chat' messages should not be construed as advice and represent the opinions of the authors, not those of London South East Limited, or its affiliates.
London South East does not authorise or approve this content, and reserves the right to remove items at its discretion.