Project and ownership
|
Share of approved capex (US$m)
|
Initial production target date
|
Production capacity (100%)
|
Quarterly progress
|
|
Petroleum projects
|
|
|
|
|
|
Macedon (Australia) 71.43% Gas
|
1,050
|
CY13
|
200 million cubic feet gas per day.
|
On schedule and budget. The overall project is 71% complete.
|
|
Bass Strait Kipper (Australia) 32.5% - 50% Gas/Gas Liquids
|
900
|
CY12(a)
|
10,000 bpd condensate and processing capacity of 80 million cubic feet gas per day.
|
On revised schedule and budget. The overall project is 97% complete.
|
|
Bass Strait Turrum (Australia) 50% Gas/Gas Liquids
|
1,350
|
CY13
|
11,000 bpd condensate and processing capacity of 200 million cubic feet gas per day.
|
On revised schedule and budget. The overall project is 79% complete.
|
|
North West Shelf North Rankin B Gas Compression (Australia) 16.67% LNG
|
850
|
CY13
|
2,500 million cubic feet gas per day.
|
On budget. Steady state production remains on track for CY13. The overall project is 94% complete.
|
|
North West Shelf Greater Western Flank-A (Australia) 16.67% LNG
|
400
|
CY16
|
To maintain LNG plant throughput from the North West Shelf operations.
|
On schedule and budget. The overall project is 15% complete.
|
|
Minerals projects
|
|
|
|
|
|
Antamina Expansion (Peru) 33.75% Copper
|
435
|
Q1 CY12
|
Increases ore processing capacity to 130,000 tpd.
|
First production was achieved in Q1 CY12. The overall project is 92% complete.
|
|
Escondida Ore Access (Chile) 57.5% Copper
|
319
|
Q2 CY12
|
The relocation of the in-pit crushing and conveyor infrastructure provides access to higher grade ore.
|
First production was achieved in Q2 CY12. The overall project is 95% complete.
|
|
Escondida Organic Growth Project 1 (Chile) 57.5% Copper
|
2,207
|
H1 CY15
|
Replaces the Los Colorados concentrator with a new 152,000 tpd plant.
|
On schedule and budget. The overall project is 13% complete.
|
|
Escondida Oxide Leach Area Project (Chile) 57.5% Copper
|
414
|
H1 CY14
|
New dynamic leaching pad and mineral handling system. Maintains oxide leaching capacity.
|
On schedule and budget. The overall project is 8% complete.
|
|
EKATI Misery Open Pit Project (Canada) 80% Diamonds
|
323
|
CY15
|
Project consists of a pushback of the existing Misery open pit which was mined from 2001 to 2005.
|
On schedule and budget. The overall project is 26% complete.
|
|
WAIO Jimblebar Mine Expansion (Australia) 96% Iron Ore
|
3,300(b)
|
Q1 CY14
|
Increases mining and processing capacity to 35 million tpa with incremental debottlenecking opportunities to 55 million tpa.
|
On schedule and budget. The overall project is 34% complete.
|
|
WAIO Port Hedland Inner Harbour Expansion (Australia) 85% Iron Ore
|
1,900(b)
|
H2 CY12
|
Increases total inner harbour capacity to 220 million tpa with debottlenecking opportunities to 240 million tpa.
|
On schedule and budget. The overall project is 59% complete.
|
|
WAIO Port Blending and Rail Yard Facilities (Australia) 85% Iron Ore
|
1,400(b)
|
H2 CY14
|
Optimises resource and enhances efficiency across the WAIO supply chain.
|
On schedule and budget. The overall project is 22% complete.
|
|
WAIO Orebody 24 (Australia) 85% Iron Ore
|
698
|
H2 CY12
|
Maintains iron ore production output from the Newman Joint Venture operations.
|
On schedule and budget. The overall project is 20% complete.
|
|
Samarco Fourth Pellet Plant (Brazil) 50% Iron Ore
|
1,750
|
H1 CY14
|
Increases iron ore pellet production capacity by 8.3 million tpa to 30.5 million tpa.
|
On schedule and budget. The overall project is 43% complete.
|
|
Daunia (Australia) 50% Metallurgical Coal
|
800
|
CY13
|
Greenfield mine development with capacity to produce 4.5 million tpa of export metallurgical coal.
|
On schedule and budget. The overall project is 56% complete.
|
|
Broadmeadow Life Extension (Australia) 50% Metallurgical Coal
|
450
|
CY13
|
Increases productive capacity by 0.4 million tpa and extends life of the mine by 21 years.
|
On schedule and budget. The overall project is 74% complete.
|
|
Hay Point Stage Three Expansion (Australia) 50% Metallurgical Coal
|
1,250(b)
|
CY14
|
Increases port capacity from 44 million tpa to 55 million tpa and reduces storm vulnerability.
|
On schedule and budget. The overall project is 45% complete.
|
|
Caval Ridge (Australia) 50% Metallurgical Coal
|
2,100(b)
|
CY14
|
Greenfield mine development and expansion of the Peak Downs Mine with capacity to produce 8.0 million tpa of export metallurgical coal.
|
On schedule and budget. The overall project is 37% complete.
|
|
Appin Area 9 (Australia) 100% Metallurgical Coal
|
845(c)
|
CY16
|
Maintains Illawarra Coal's production capacity with a replacement mining domain and capacity to produce 3.5 million tpa of metallurgical coal.
|
Approval announced. See News Release dated 22 June 2012.
|
|
RX1 Project (Australia) 100% Energy Coal
|
400
|
H2 CY12
|
Increases run-of-mine thermal coal production by approximately 4 million tpa.
|
First production was achieved in Q2 CY12, significantly ahead of schedule and on budget. The overall project is 85% complete.
|
|
Cerrejon P40 Project (Colombia) 33.3% Energy Coal
|
437
|
CY13
|
Increases saleable thermal coal production by 8 million tpa to approximately 40 million tpa.
|
On schedule and budget. The overall project is 35% complete.
|
|
Newcastle Third Port Project Stage 3 (Australia) 35.5% Energy Coal
|
367
|
CY14
|
Increases total coal terminal capacity from 53 million tpa to 66 million tpa.
|
On schedule and budget. The overall project is 43% complete.
|