MELBOURNE, June 22 (Reuters) - BHP Billiton is likely to cut the first sta
ge of its estimated $10 billion iron ore port expansion in half, analysts and investors said, as it looks to slash capital spending due to rising costs and an uncertain market outlook.

The Outer Harbour project in Western Australia is one of three mega projects in an $80 billion pipeline that BHP has slowed, under pressure from shareholders who want bigger dividends and buybacks rather than expensive projects with no short-term returns.

In February, BHP committed $779 million in early funding to build a 100 million tonnes a year outer harbour facility and said at the time it would be reviewed for full approval in the December quarter this year.

Five analysts and two investors said on Friday BHP's incoming iron ore chief, Jimmy Wilson, would have to cut plans for the Outer Harbour.

'He's been told he's got to re-cut it to a smaller project,' UBS analyst Glyn Lawcock said.

They predicted the logical outcome would be to cut the first stage of the expansion to 50 million tonnes a year from 100 million tonnes a year.

Analysts and investors said given that BHP has about 50 million tonnes a year extra rail capacity, the company was likely to look for ways to milk its existing mines for extra output to fill that capacity, in which case it would only need 50 million tonnes a year of new port capacity.

'They're looking at it as 50 million tonnes a year,' said another analyst, who declined to be named because they were not authorised to speak to the media.

BHP Billiton declined to comment on whether its incoming iron ore chief had been told to cut the scope of the outer harbour project. A spokesman directed Reuters to recent comments by senior BHP managers on the company putting the brakes on spending plans.

Wilson's move into the iron ore job officially from July 1 creates an opportunity for a review of the Outer Harbour plan, looking at ways to stretch the existing operations before splashing out on the massive port, analysts and investors said.

'Maybe a new pair of eyes looking at it will come up with alternative ways of doing things,' said Tim Barker, a portfolio manager at BT Investment Management.



RIO TINTO EXTENDS LEAD

The Outer Harbour is crucial to BHP's long-term plan to nearly double its iron ore capacity to 440 million tonnes a year, a project that had been expected to take eight years at a cost analysts estimated at more than $20 billion.

When fully built, the development would include a four km-long jetty, a four-berth wharf and a 32-km shipping channel to handle 200 million tonnes a year of iron ore, adding to 240 million tonnes capacity BHP is targeting in an inner harbour expansion already underway.

'Anywhere they can take smaller bites, they will,' said CLSA analyst Hayden Bairstow.

Under its existing plan, analysts estimate the capital cost of the expansion would be around $200 per tonne of iron ore capacity.

That puts it at a sharp disadvantage to world no.2 iron ore miner Rio Tinto, which this week committed to spend $3.7 billion to expand its Australian iron ore operations to 353 million tonnes a year by the first half of 2015, up from 283 million tonnes from an expansion underway.

Analysts estimate its capital cost at around $160 per tonne of added capacity.

In a dig at its arch rivals BHP and Vale, which last year postponed its $8 billion Serra Sul project by two years, Rio said its Pilbara project stacked up under any likely scenario, underpinned by Chinese demand growth.

'This demand growth is coupled with an increasingly challenged supply response, as several high-profile competitor projects have recently been either delayed or postponed,' Rio Tinto's iron ore chief Sam Walsh said in the expansion announcement.

BHP's shares fell 2.1 percent on Friday to A$31.52, hovering near a three-year low hit earlier this month.

Shareholders who have been clamouring for bigger dividends or share buybacks said they would be comfortable with a smaller spend on the Outer Harbour project, if it helped improve the near term returns.

'As an investor you want to see them get the greatest bang for their buck,' said BT Investment Management's Barker.



(Editing by Ed Davies) Keywords: BHPBILLITON IRONORE/

(Sonali.Paul@thomsonreuters.com)(+61 3 9286 1419)(Reuters Messaging: sonali.paul.thomsonreuters.com@reuters.net)

COPYRIGHT
Copyright Thomson Reuters 2012. All rights reserved.
The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.


Related Shares: Bhp Billiton Plc (BLT) 





UPDATE 1-Rio Tinto to cut over 40 jobs in Australian iron ore unit

* Rio Tinto says move will help 'delayer' some management roles* Company employs around 10,000 in Australian iron ore divisionSYDNEY, June 19 (Reuters
[13 Hours Ago]

UPDATE 3-Brazil mine bill would double top royalty rate

* Bill to require rights to be developed or lost * Introduces auction system for some mining prospects * Vale CEO says would have "major impac
[Yesterday 21:44]

CORRECTED (OFFICIAL)-UPDATE 2-Brazil mine bill proposes royalty hike

(Government corrects royalty figure to say it will be up to 4 percent with some exceptions in 8th and 9th paragraphs (not 0.5 percent to 4 percent)
[Yesterday 21:32]

UPDATE 1-New Zealand/Australia Morning Call-Global markets

-----------------------(06:33 / 2033 GMT)----------------------- Stock Markets S&P/ASX 200 4,814.35 -11.53 NZSX 50 4,462.10 +14.47
[Yesterday 20:39]

Brazil mining bill could double royalty to 4 pct

RIO DE JANEIRO, June 18 (Reuters) - Brazil unveiled a long-awaited bill to reform the country's 46-year-old mining code on Tuesday, proposing new roya
[Yesterday 15:03]

COLUMN-Is China backtracking on attempts to control iron ore?: Clyde Russell

--Clyde Russell is a Reuters market analyst. The views expressed are his own.--By Clyde RussellLAUNCESTON, Australia, June 17 (Reuters) - It may be to
[Mon 05:45]

RPT-UPDATE 1-China to scrap iron ore import licence system -source

* China to ditch one-decade iron ore import licensing from H2* Companies only require routine licenses to import iron oreBy Ruby Lian and David Stanwa
[Thu 22:01]

UPDATE 1-China to scrap iron ore import licence system -source

* China to ditch one-decade iron ore import licensing from H2* Companies only require routine licenses to import iron oreBy Ruby Lian and David Stanwa
[Thu 11:44]



Sign up for Live Prices





Datafeed and UK data supplied by NETbuilder and Interactive Data. While London South East do their best to maintain the high quality of the information displayed on this site,
we cannot be held responsible for any loss due to incorrect information found here. All information is provided free of charge, 'as-is', and you use it at your own risk!
The contents of all 'Chat' messages should not be construed as advice and represent the opinions of the authors, not those of London South East Limited, or its affiliates.
London South East does not authorise or approve this content, and reserves the right to remove items at its discretion.